The Schedule and What Always Slips

Improve · Lesson 2.8 · 6 minutes · Captions on by default, press CC to turn them off

Full lesson transcript

The printed schedule pinned to the site office wall has forty lines, and fewer than half of them are fully in the contractor's control. Look at it the way a superintendent does. Forty activities, each one a bar with a start and a finish. Demolition, framing, rough plumbing. It looks like a plan the contractor owns.

But read the lines one at a time and ask who actually decides when each one happens. The building department decides when the permit is issued and when the inspectors arrive. Manufacturers decide when equipment ships. The utility company decides when the power is connected. A tenant decides when its own drawings are ready.

The weather decides some of it. The owner decides when finishes are chosen. The contractor controls its own crews and its subcontractors. That is the rest. A construction schedule is the overarching plan for the order and timing of every task on a job, from permit to handover.

This chart shows how those tasks link together. Inside it sits the idea that matters most: the critical path, the chain of tasks where any delay pushes back the final finish date. Most tasks have some slack. Tasks on the critical path have zero. Painting a back office might be able to slip a week without moving anything because nothing waits on it.

The electrical panel cannot slip a day. The inspector will not sign off the walls until it is in. The drywall cannot close until the inspector signs, and everything after drywall waits on that. It is the exact same schedule, but you have very different consequences for the same week of delay, depending entirely on whether that task sits on the critical path. Five things slip again and again.

They disrupt the schedule on nearly every job. First, permits. Review times vary widely by jurisdiction and by season. A permit expected in four weeks can easily take ten. Because it sits at the very front of the schedule, every day it slips means the whole job slips.

Next are long lead items. These are equipment and materials that take a long time to arrive after they are ordered. Electrical switch gear, rooftop units, custom glass. Lead times run many weeks or months, and they fluctuate with the market. Third, inspections.

Each one has to be requested, scheduled, and passed before work can cover it up. A single failed inspection means a fix and a new request, forcing the work behind it to wait. Fourth, owner decisions. Finish selections, change approvals, and answers to the contractor's questions. Owners are often the slowest party on a job without realizing it.

Every question sitting unanswered on a desk is a question a crew is waiting on. There is a simple rule to stop being the bottleneck. At the start of the job, ask the contractor for a firm deadline for every decision you need to make. Tile by this point, light fixtures by that one. Then make those decisions early while there is still time to change your mind.

Finally, utilities and weather. New power or water service runs on the utility company's calendar, not yours. And exterior work wait on weather, which no schedule can perfectly forecast. Schedules rarely slip because the crew was slow. It happens because uncontrollable external dependencies arrive late and the work behind them has to wait.

This brings us to a specific scheduling mistake, promising a tenant the contractor's absolute best case scenario. Take an owner who signs a lease with a new tenant, promising delivery of a finished space by a fixed date. The date comes straight from the contractor's first schedule, which assumed a fast permit and on-time equipment. The lease includes a penalty, a day of free rent for every day the delivery is late. The permit takes six extra weeks.

The rooftop unit arrives a month late. Delivery slips by ten weeks. The free rent penalty alone comes to twenty thousand dollars, and the owner spends the rest of the job worried the tenant will abandon the lease entirely. The fix here is not a better contractor. It is a better promise.

Build in schedule contingency. Extra time held at the end of the schedule, just as the budget holds extra money. On a renovation, add a ten to twenty percent buffer on top of the contractor's duration before committing a date to a tenant. You also protect the schedule by ordering long lead items as early as the design allows. That might even be before the permit is issued, if the design is settled enough and the architect agrees.

The same thinking belongs in the lease itself. A delivery date tied to an event, like a set number of days after the permit is issued, is much safer and more honest than a fixed date on a calendar. Your promise to a tenant must remain flexible. It should move in tandem with the things that actually dictate the pace of the job. There is one exact question to ask the contractor when the first schedule arrives.

Here are the words: Which three items on this schedule, if they slip, move the finish date? A good superintendent will answer immediately. Their answer tells you where the critical path runs, which items to order first, and which decisions you personally must not delay. Watch for one major warning sign, a schedule with no permit date and no inspections on it. That document is describing a fantasy project where nothing outside the contractor's crews goes wrong, which is not a real job.

A schedule is a promise made by people who do not control half of it. Plan for the half they do not. You can now estimate costs and map protective schedules for a project. The next section covers hiring contractors and reading their bids.