Improve · Section 2: Scoping the Work · Lesson 2.7
Budgeting With a Real Contingency
Full lesson transcript
An owner budgeted a lobby renovation to the dollar, and the first wall the crew opened spent the entire cushion. This is a composite, but every owner who has renovated an older building will recognize it. The budget was careful. Every finish was priced. The contractor's bid was fixed.
Then demolition started. Behind the old paneling, the crew found wiring that no longer met code. Under the old tile, the slab had a crack. Above the ceiling, a drain line from an upstairs restroom had corroded through. None of it was anyone's fault, and none of it was visible before the walls came open.
And every dollar of it was real, and it demanded immediate capital. To pay for wiring the tenants would never see, the owner cut the finishes they would see every day. A contingency is money set aside in a budget for costs you know will come but cannot yet identify. It is a dedicated line for the unknown. And the size of the unknown depends entirely on the building's hidden realities, not on the owner's mistakes.
There are illustrative benchmarks commonly used as starting points. For new construction on a clear site with complete drawings, many owners carry roughly five percent. For renovating a newer building in good condition, that starting point moves to roughly ten percent. For renovating an older building where walls, floors, and ceilings will be opened, set aside fifteen to twenty percent, sometimes more. Two things push the number up, whatever the building's age.
Incomplete architectural drawings because every gap gets filled later at a later price. And a tight schedule because there is no time to comparison shop when a surprise appears. Two things push it down. Real investigation before bidding, like opening a few small test holes to see what is behind them, and possessing a verified historical knowledge of the property. These percentages are not arbitrary rules.
They're the defensive ranges experienced owners use to accurately price risk before the true condition of the property is exposed. Before calculating the contingency, the base budget itself has to be complete. It sits on three distinct layers. First are hard costs, the physical construction itself. This includes labor, materials, and the contractor's overhead and profit.
Second are soft costs, everything that is not construction but that the project cannot happen without. Design fees, permits, insurance, and the interest you pay while the work is underway. As an illustrative benchmark, these often run fifteen to twenty-five percent of hard costs. Third are owner costs. These are requirements outside the contractor's purview.
Moving tenants, rent loss during the work, and leasing commissions to fill the space afterwards. Failing to layer all three categories leaves a massive gap. An owner who only budgets the contractor's bid is drastically underfunded before a single wall is opened. This chart shows how a complete budget is assembled, starting with an older building and a contractor's bid of three hundred thousand dollars. Soft costs at twenty percent add another sixty thousand dollars, stacked on top of the bid.
Owner costs, commissions and lost rent, add another forty thousand, bringing the total before contingency to four hundred thousand. Now calculate a fifteen percent contingency on that entire sum. That adds sixty thousand dollars, for a true final budget of four hundred and sixty thousand dollars. The amateur owner believes the job costs three hundred thousand. The professional knows it costs four hundred and sixty.
Running this comprehensive math is the only way to evaluate if the end rent actually justifies the project before you sign any contracts. There are usually two contingencies on a project, doing very different jobs. The contractor may carry one inside its bid for its own internal pricing risk. The owner carries another for the building's unknowns and for late decisions. Hold the owner's contingency entirely outside the contractor's contract sum.
Money that sits inside the contract tends to get spent there. A lender may set a minimum contingency floor. That number protects the loan. Your number has to protect the project itself. Physically and contractually separating these funds ensures one thing.
The owner retains total veto power over what qualifies as a legitimate hidden cost. That veto power requires strict behavioral discipline. Contingency pays strictly for unknowns. It does not pay for choices. When a new cost appears, use this exact diagnostic phrase.
Ask, "Is this something the building told us or something we decided?" A corroded pipe behind a wall is the building telling you. Contingency pays. Upgrading the lobby tile because the new samples look better is a decision. That choice must be funded from somewhere else or rejected. The primary behavioral mistake happens gradually during the quiet early days of a project.
The job is going well, and the owner treats the untouched, unused contingency money as a discretionary upgrade fund. Take an illustrative forty thousand dollar contingency. You spend twenty-five thousand on early elective upgrades. Then the crew opens the back wall and finds a thirty thousand dollar problem. You are now fifteen thousand short.
Blending risk money with choice money destroys the project safety net. It leaves the owner trapped with sunk costs in finishes and no money left for critical infrastructure. The discipline requires releasing contingency should be released in roughly the order that physical risk is retired on the site. Leave the funds mostly untouched until demolition finishes, the ground is dug, and the hidden conditions are fully exposed. Watch for this critical red flag.
If money is leaving the contingency account before demolition is complete, it is almost certainly paying for elective choices. A little money left at the end of a project is not a waste of capital. It is the ultimate mark of an honest budget sized for reality. A contingency is money for what the building has not told you yet. Spend it only when the building speaks.