Underwrite · Section 3: Commercial Financing · Lesson 3.6
Construction Loans and the Draw Schedule
Full lesson transcript
The construction loan commitment on the conference table says two million dollars, and not one dollar of it moves until someone inspects the work. That is the first surprise for most people who build. A construction loan pays for a building while it is being built. The funds sit with the lender, and you earn it piece by piece by proving that the work it pays for exists. The reason is the collateral itself.
On a finished building, the lender lends against something that already earns rent. On a construction loan, at the start, there is only land and a set of plans. If the project stopped halfway, the lender would own a partly built structure that nobody can use. To protect against that, the lender releases money only as fast as the physical building actually rises out of the dirt. The document that governs all of this is the loan agreement.
It breaks the entire process down into three critical parts. The first is the budget. Every cost of the project is broken into line items. You have hard costs, the physical construction like concrete and steel. Then you have soft costs, expenses like design, permits, and loan interest.
Soft costs are easy to underestimate, but a budget that is careless about them runs out of money just the same. Lenders also expect a contingency. This is money set aside for what nobody predicted. Illustrative, lenders often want a contingency of roughly five to ten percent of the physical construction costs built right into the budget. The second is the equity requirement.
Most construction lenders require the borrower's own money goes into the project before the lender's money activates. On a three million dollar project where the lender commits two million, the borrower's one million is spent before the loan pays for anything. Construction lenders usually lend a share of the total cost, often somewhere around sixty to seventy-five percent. They demand to see your money securely in the ground first. This ensures the finished building will be worth comfortably more than the final loan.
The loan amount and the equity requirement set the boundaries of the deal. But the actual survival of the project depends entirely on the third part, the recurring day-to-day reality of moving the money. The third is the draw process. A draw is a single request, usually made once a month, to release part of the loan to pay for work that has just been completed. Usually once a draw, the general contractor prepares a massive paperwork package.
They prepare a detailed payment application paired with all subcontractor invoices. The borrower reviews the package and sends it to the lender. The lender then deploys an outside inspector to physically walk the site and confirms that what the requested work actually exists. If the application says framing is sixty percent complete and the inspector only sees forty percent, the draw is ruthlessly cut to forty. There is also retainage.
Roughly ten percent of every payment is deliberately held back by the lender to keep the contractor committed through the last punch list. This entire cycle places a severe financial strain on your general contractor. They must often float a month or more of work on its own credit while waiting for the draw to process. A contractor buckling under that strain works slower and is tempted to cut corners on the physical build. An efficient, predictable draw process directly dictates whether a building gets built well or poorly.
Now, the single mistake that damages the most projects, letting the construction loan go out of balance. In balance means the lender's strict calculation shows the money left in the loan, plus any remaining equity, is exactly enough to finish the building. Imagine the project is halfway done. Framing materials come in higher than budgeted and the contingency is already used up. The lender recalculates and finds the remaining loan is two hundred thousand dollars short.
The moment the loan is now out of balance, the lender instantly stops all draw funding until the borrower deposits the missing two hundred thousand in cash. The fallout cascades immediately. Contractors stop getting paid. Subcontractors walk off the site. Interest piles up.
And a borrower without cash reserves can lose the project entirely. The prevention is dull and effective. Build a real contingency. Submit strictly honest draws so the inspector trusts you. And before you break ground, ask your lender this exact question.
What do you need in every draw package and how many days from submission to funding? The answer sets your cash plan. Get signed lien waivers from every subcontractor and supplier. If a subcontractor is not paid by the contractor above them, they can legally halt your next draw by claiming against the property, even if you already wrote the check. A construction loan is a promise to pay for work that has already been proven.