The Deal Point Nobody Discusses Until Too Late

Lease · Lesson 5.7 · 5 minutes · Captions on by default, press CC to turn them off

Full lesson transcript

A landlord and a tenant agreed on the rent, the term, and three free months, and then discovered they had never agreed on when any of it started. The suite was about twenty-five hundred square feet. At an illustrative twenty-four dollars a foot, that is sixty thousand dollars a year or five thousand dollars a month. The lease gave the tenant three months free. The landlord read that to mean three months free from the day the tenant got the keys.

Simple. Hand over the space, wait three months, and start collecting. The tenant read it differently. The lease also said the tenant would open for business after completing its improvements. Permits took four months.

Construction took three more. The tenant opened seven months after getting the keys and claimed its three free months from there. The landlord expected rent to begin three months after handing over the keys. The tenant started paying ten months after. That is seven months apart.

At five thousand dollars a month, that is a thirty-five thousand dollar disagreement sitting in one word that both sides had read and neither side had discussed. This is the deal point that tends to be settled last if it is settled at all. Everyone negotiates the rent Everyone negotiates the free months. Very few people slow down on the date the money actually starts, and the answer to that question can be worth as much as all the others. It gets left late for understandable reasons.

At the letter of intent stage, both sides are excited and the opening feels close. Nobody has hired a contractor yet. Nobody has sat in the permit office. The dates feel like details for the attorneys. The fix for a disputed start date begins with seeing that a lease has three different dates.

The delivery date, the day the landlord hands over the space in whatever condition the lease requires. The commencement date, the day the lease term officially begins. The clock on the five or ten years starts here. And the rent commencement date, the day rent is actually due. On most retail and many office leases, they do not fall on the same day.

The tenant takes delivery, spends months on permits and construction, and only then starts paying. That gap is normal and often fair. A tenant cannot earn money in a space that is still a construction site. The problem is not the gap. The problem is a gap with no end.

Here is the rule for when rent starts. Rent starts on the earlier of two dates, the day the tenant opens for business or a fixed number of days after delivery. Illustratively, you might set that outside date at about one hundred and twenty days for a typical small retail build-out. The fixed number is the part that protects you. If the tenant opens quickly, rent starts when they open.

If permits drag or the tenant simply changes their mind about opening, rent still starts on a known day. The risk of delay sits with the party who controls the delay. The tenant controls its contractor, its permits, and its opening. The landlord controls delivery. The right number depends on the space and the market.

A simple retail suite might need ninety days. A restaurant with a kitchen and grease trap might need six months. Ask your leasing broker what similar build-outs in your market typically take and set the number to match with a small cushion. A tenant who cannot open within a fair window is telling you something about their plan. Here are the words to settle the rent start date at the letter of intent before anyone drafts anything.

Rent starts on the earlier of the day you open or one hundred and twenty days after we hand you the keys. Does that fit your permit timeline? The question at the end matters. It invites the tenant to tell you now if their timeline is longer. If it is, you can agree on a longer window with open eyes.

What you avoid is finding out in month seven. Two related points belong in the same conversation. First, the delivery condition, or what state the space is in when you hand it over. Second, what happens if the landlord must finish work before delivery and is late? Agree on these in advance so a late landlord and a slow tenant are treated by the same rule.

Now, the mistake. It has a name, the open-ended start. Rent begins on opening or completion of improvements with no outside date. It feels flexible and friendly when the lease is signed. It becomes very expensive later.

What does it cost? In the composite, thirty-five thousand dollars of rent the landlord expected and did not receive. Add a leasing commission paid at signing, taxes and insurance carried on a suite producing no income, and the attorney's time to argue about one word. And the worst version is the tenant who never opens at all. With no outside date, the landlord can be left holding a signed lease, a half-built suite, and no rent while arguing about whether the rent obligation has even begun.

Watch for any start date that depends on an event instead of a day. Standing alone, it is a date nobody controls. Agree on when the rent starts as carefully as you agree on how much it is.