Improve · Section 3: Contractors and Bids · Lesson 3.6
Retainage, Lien Waivers, and Protecting Title
Full lesson transcript
The payment request on the desk asks for eighty thousand dollars, and the most important number on it is the eight thousand the owner is going to hold back. That request has a name a payment application, the contractor's formal bill for the work completed so far. On most commercial jobs, contractors bill as the work progresses. Behind it sits the schedule of values. That is the list, agreed at the start, that breaks the contract price into pieces.
Demolition so much. Framing so much. Electrical so much. Each month, the contractor reports what percentage of each line is done and bills for that share. Your job is to walk the site and check that the percentages are true.
If the application says drywall is seventy percent complete, you should be able to see roughly seventy percent of the drywall. Looking at this chart, you can see how that invoice breaks down. Retainage, a portion of each payment that the owner holds back until the job is finished. Ten percent is common. Illustratively, on that eighty thousand dollar application, ten percent retainage means the owner pays seventy-two thousand now and holds eight thousand.
Over a whole job, that held money adds up. On a four hundred thousand dollar contract, it can reach forty thousand dollars by the end. Why hold it? Because the last few percent of any job is the hardest to get finished. The punch list, the final inspection, the warranty paperwork.
Retainage is the reason a contractor comes back to do it. State laws limit how much retainage can be held or how quickly it must be released. A construction attorney in your state can tell you what applies. Managing this pool correctly is your primary tool for guaranteeing a finished building. Now the harder part, protecting title.
A mechanic's lien, a legal claim against your property by someone who improved it and was not paid. Here is the part that surprises owners. In many states, the claim can come not only from the contractor you hired, but from their subcontractors and suppliers too. The electrician your contractor hired, the supply house that delivered the drywall, even if you paid your contractor in full. A lien sits on the title to your property.
While it is there, you may not be able to sell or refinance cleanly. Your lender will want it resolved. In some cases, the unpaid party can go further. and ask a court to enforce it against the property So. Paying your contractor is not the same as making sure everyone on your job got paid.
If the money stops at the contractor, your title is dangerously exposed. That is where the document that protects you comes in. A lien waiver, a signed statement from a contractor or supplier giving up their lien rights for work that has been paid. Waivers come in two kinds, and the difference matters. A conditional waiver says, in effect, "I give up my lien rights for this amount once the payment actually clears." You collect conditional waivers with a payment request.
An unconditional waiver says, "I have been paid this amount, and I give up my lien rights for it." Full stop. You collect unconditional waivers once the money has securely landed. Here is the baseline decision rule for paying a contractor. Do not release a payment without a conditional waiver for this payment from the general contractor. And you demand unconditional waivers for the previous payment from the contractor and from every subcontractor and supplier above a threshold you set in the contract.
Illustratively, anyone whose work on the job exceeds ten thousand dollars. Here is how to ask for it word for word. With this payment application, please include your conditional waiver for this payment and unconditional waivers from you and your major subcontractors and suppliers for the last one. That way, each month, you are confirming that last month's money actually reached the people who did the work. Two more tools are worth knowing by name.
The preliminary notice. In many states, a subcontractor or supplier sends the owner a notice early in the job saying they are working on it. Owners often throw these away as junk mail. Do not. Each one is a list of people you should be collecting waivers from.
The second is the joint check. When you are worried a subcontractor might not be paid, you can issue a single check made out to both the contractor and that sub. Neither can cash it without the other signing. It is a little slower. It is also very hard to divert.
Owners usually save it for a large supplier or a contractor slow to pay. Here is the lien mistake. Call it paying twice. An illustrative case. An owner pays the general contractor promptly every month without collecting waivers from anyone below them.
Near the end of the job, the contractor runs into money trouble on another project and uses part of this owner's payments to cover it. The electrical subcontractor is left unpaid forty thousand dollars. The electrician files a lien on the owner's building. The owner already paid for that electrical work once through the contractor. Now, to clear the title and keep a refinance on schedule, the owner pays the electrician forty thousand dollars again and then tries to recover it from a contractor who may not have it.
Every step of that sequence could have been caught with one sheet of paper a month. At the end of the job, the same logic applies with more weight. Before you release retainage, collect final unconditional waivers from the contractor and every significant sub and supplier. Retainage is your last leverage. Once it is paid, you have very little left.
Watch for this. A payment application where the percentages complete run ahead of what you can see on site. Billing ahead of the work is how retainage and waivers get quietly undermined because you end up holding back ten percent of money you should not have paid yet. Walk the job before you pay every time. Paying your contractor is not the same as paying for your job.
The waivers are how you know the difference.