Improve · Section 3: Contractors and Bids · Lesson 3.2
Getting Three Real Bids
Full lesson transcript
Earlier, you learned to write a scope a contractor cannot misread. Here is where it breaks. Three bids come back, and they are priced on three different jobs. A clear scope is necessary. It is not enough.
Contractors do not only read your scope. They read the site, the owner, the schedule, and how badly they want the work. Then they send back a number shaped by all of it. If each contractor walked the building on a different day, heard different answers, and priced on their own format, you do not have three bids. You have three opinions about three slightly different projects.
A real bid has a handful of properties. First, every bidder prices the same scope. in the same words with the same drawings if there are drawings. Nobody gets a verbal version over the phone. Second, every bidder uses the same bid form.
A bid form is a simple page you send out that breaks the job into the same lines for everyone. Demolition, framing, electrical, plumbing. One of those lines deserves its own name: general conditions. The contractor's cost of running the job itself, things like supervision and temporary protection. Contractors bury it in different places, so your form should ask for it by name.
When everyone fills in the same lines, you can lay the bids side by side. and see exactly where they differ. Third, everyone walks the site, ideally together at one scheduled walk. That way, they all see the same ceiling. They see the same electrical room and the same occupied suite next door, and they all hear the same answers to the same questions.
Fourth, every single question gets answered to everyone. When one bidder asks a question, the answer goes to all of them in writing the same day. That written answer has a name, an addendum, a numbered clarification or change to the bid documents. Every bidder receives it. Watch out for a bidder who calls you privately with a question and asks you not to share the answer.
The moment you answer only one bidder, the bids stop comparing. Answer the question, thank them for it, and send the answer to everyone. Fifth, the same deadline and the same validity. Ask that each price holds for a stated period, often thirty to sixty days. Material prices move.
You wanna know how long the number is real. Give them enough time. A rushed bid is a padded bid. When a contractor has only a few days to price a job, they guess high to protect themselves. As an illustrative benchmark, a small commercial job usually deserves two to three weeks of bidding time.
Here is the phrase that sets up a fair round of bids. Put it in the request and say it again at the site walk. "Please price the attached scope exactly as written on this form, and list anything you would do differently as a separate alternate with its own price." An alternate, a priced option outside the base bid. You can accept or decline it. Good contractors often have better ideas.
You want those ideas. You just want them priced separately, so the base bids still compare. Here is the rule for comparing bids. Compare the highest and lowest. If the spread is more than twenty percent on a well-defined scope, stop.
A spread that wide means somebody read the job differently. Find out who and why before the numbers mean anything. Often one bidder is someone you would actually hire. Here is the bidding mistake: the courtesy bid. A courtesy bid often arrives late on the contractor's own letterhead with very little detail and a number far above others.
Contractors rarely say no to an owner they might wanna work for later, so when they are busy, they send a high number anyway. High enough that they will not win, low enough that it does not look rude. It keeps them on your list. For example, an owner bids out a two-hundred-thousand-dollar tenant improvement. One contractor sends a courtesy number.
The real bidders know the field is thin, so nobody sharpens their pencil. With three hungry bidders, it comes in ten percent lower. Twenty thousand dollars lost. The fix for a courtesy bid is simple and polite. Before you send the scope out, call each contractor.
Ask, "Do you have the capacity and the interest to take this job in the timeframe we need?" A contractor who wants the work will say so. One who does not will thank you, and you can invite someone else. If you cannot find three contractors you would honestly hire, it is better to invite four or five and expect one to drop out than to accept a decoration. This applies to a bathroom remodel and to a full building renovation. The principles do not change.
Three bids only count as three when all three are pricing the same job and all three want it.