Construction Financing in Practice

Improve · Lesson 5.7 · 6 minutes · Captions on by default, press CC to turn them off

Full lesson transcript

A developer walked out of a draw meeting with about half the money that she had asked for, and the building was exactly as far along as she had said. This is a composite. The details are drawn from many projects, and nearly every developer has lived some version of it. The contractor billed for work, the lender approved a fraction of it. Nobody lied.

The lender simply saw the project through a different set of rules than the developer did. The loan mechanics themselves are covered in the companion course Underwrite. That covers how a construction loan is sized and how interest accrues. The subject here is living inside one, what it feels like month after month from the developer's side of the table. On that particular morning, the difference between those two sets of rules was hers to cover.

The daily reality of a construction loan is that the developer is personally responsible for the cash gap between what the building needs and what the lender provides. Equity goes in first. On most construction loans, the developer's own money and the partner's money must be spent entirely before the lender funds a single dollar. On an illustrative ten million dollar project with a loan of about six and a half million, the first three and a half million is all equity. That money pays for land, design, fees, and early site work.

The lender wants to see that money in the ground. They require invoices and physical proof of payment before their own capital is released. The developer carries the entirety of the project's early risk alone. The lender's money arrives only when the building is already partly real. The draw is a monthly request for loan money to pay for work finished.

The general contractor submits a pay application, a document listing every line of the construction budget and how much of each is complete. The developer reviews it and adds soft costs, like the architect's invoice and permit fees. Then they send the whole package to the lender, and they meet to agree line by line on what gets paid. Most construction lenders hire their own construction consultant, an independent inspector who visits the site each month and reports strictly to the lender, not to you. The inspector checks whether the work billed is actually in place and matches the drawings.

If the contractor bills sixty percent of the roofing and the inspector sees forty, the lender funds forty. Materials stored off-site are often not funded at all until they arrive. You can solve this by changing one habit. Have the contractor walk the site with the inspector to agree on site before the pay application is ever submitted. The inspector is not your adversary, but their job is to protect the lender's money, and that strict mandate produces cuts.

That creates a permanent cash flow gap, and that gap lands directly on the developer. Retainage and lien waivers run through every monthly draw as well. Retainage, a share of each payment held back until the work is complete, protects the lender. Lien waivers protect the title. Now the part that decides whether a project survives, cost overruns and who funds them.

Almost every construction loan includes a balancing requirement. The loan must stay in balance. The money left in the loan, plus any equity still to come, must always be enough to finish the project. If costs rise, the remaining money is no longer enough. The loan is out of balance.

The lender will immediately stop funding draws until the developer deposits the cash difference. Behind that sits the completion guarantee, a personal or corporate promise from the developer to the lender the building will be finished, whatever it costs. It is the reason overruns come out of the developer's pocket. Ask a real estate attorney to explain it before you sign one. The combination of the balancing requirement and the completion guarantee ensures that the ultimate survival of the project relies entirely on the developer's personal liquidity.

Here is the decision rule for a construction loan's contingency. The percentage of the contingency budget spent should not run ahead of the building's physical percent complete. If the building is forty percent finished and seventy percent of the contingency is gone, the project is on course to run out of money. Experienced developers follow a specific benchmark. Hold liquid cash outside the project, often somewhere around five to ten percent of the total budget for rebalancing calls.

There is one question worth asking at every single draw meeting. Here are the words. "Walk me through what the inspector would not approve and why." It turns a financial cut into vital information. It exposes whether the contractor is billing ahead or that a budget line is running out well before it becomes fatal. The ultimate mistake inside a construction loan is having no cash available for a rebalancing call.

Consider an illustrative example. Prices rise mid-project and costs come in four hundred thousand dollars over what the loan and contingency can absorb. The lender declares the loan out of balance and stops funding. The developer has no reserve. Unpaid slows the job Subcontractors file liens.

Within a few months, the developer brings in a partner who provides the four hundred thousand in exchange for a large share of the profit or control of the project. The overrun was four hundred thousand dollars. The real cost was the forced surrender of ownership. These financial mechanics scale down to smaller projects. If you are building a single house, watch for a pay application that runs ahead of the inspector month after month.

A continuous gap means the contractor is using your draws to finance their own cash flow. A mismanaged construction loan ends with the permanent loss of the developer's equity, ownership, and control over the asset they built. The lender funds the building as it gets built. The developer funds everything that goes wrong along the way.