Evaluate · Section 4: Capital Decisions · Lesson 4.7
Measuring Whether a Project Worked
Full lesson transcript
Did the new parking lot lights actually save what the contractor said they would? Most owners never find out. The project gets approved on a promise, the work gets done, the invoice gets paid, and then everyone moves on to the next thing. The promise that justified the spending is almost never compared to what actually happened in the real world. That matters for one reason.
It creates a vacuum of accountability. If you never check the last promise, you're totally unprepared to evaluate the next capital proposal. The next request is coming. It may come from the exact same contractor. It might rest on the exact same kind of assumption.
Without a system to verify the past, you have zero baseline. You have no idea how much to trust the future promises you already have. Every project approved on a number made a promise in that number. The lights would save ten thousand dollars a year. The new rooftop units would cut repair calls in half.
The promise is the thing to measure against. Start by finding that exact number inside the original proposal or the approval email. Measuring success does not require a complex new system. It only requires retrieving that original promise and measuring against it at the right moment. For most projects, that is exactly one full year after completion.
That is long enough to cover every season since utility costs swing with summer and winter. It is short enough that the details are still clear. For. Rent projects are the exception. You check those after the first few renewals.
Rent only moves when new leases are signed. Here is the exact request to make to the property manager. Show me the twelve months before this project and the twelve months after it on the same line of the statement side by side. Every part of that sentence matters. Twelve months ensures every season appears.
The same line of the statement so you compare electricity directly to electricity, not total expenses to total expenses. Notice who is asked. The property manager. They hold the statements and have no stake in the answer. You never ask the contractor who sold the project.
A person measuring their own promise will tend to find reasons it came true. This single request isolates the truth. It uses numbers you already possess, bypassing bias entirely. Now you adjust for what else changed. A year is long.
If the utility raised its rates, the final bill may have fallen less than the savings. The project did exactly what it promised, and a rate hike makes it look like a failure on paper. Plenty happens besides the project. A center that went from eighty percent to ninety-five percent leased will use more traffic and more wear. An unusually hot summer drives up common area power.
For energy projects, the cleanest comparison is in the physical units, not the dollars. Look at the kilowatt hours before and after. That removes the utility rate change completely. None of these variables are excuses. Adjusting for them is the crucial difference between measuring the actual project and blindly measuring the entire year.
Set a project's result against the promise. Here is the decision rule. If the result comes in near the promise roughly eighty percent of it or better, the project worked. The promise was sound. If it comes in under about half, a core assumption was wrong.
You want to know what failed before approving the next project that rests on the same assumption. Run this rule against the final cost too. A project that saved every dollar it promised but cost forty percent more than quoted did not deliver the return that got it approved. Defining what counts as working in advance is the only way to safeguard your next capital spend. This brings us to a named mistake.
Judging a capital project by feel or by its first month. An owner replaces three old rooftop units on a promise of eight thousand dollars in annual savings. The first month after installation is mild weather. The bill is dramatically lower and the owner feels pleased. Operating on that premature feeling, the owner instantly approves a massive proposal to replace five more units.
An illustrative one hundred twenty thousand dollar spend resting on the same promised savings rate. But the first month was mild weather, not efficiency. Across a full year compared line to line, the actual savings were closer to three thousand dollars. The contractor vastly overestimated how badly the old units were running. Skipping a single one-year comparison led directly to a six-figure commitment built on an entirely false assumption.
A result that falls short is not an accusation. It is not a reason to assign blame. It is simply vital information required to correct the assumption before the next bid. Watch out for false measuring sticks. Six months compared to twelve months, a winter compared to a summer, total expenses instead of the single impacted line.
If anyone presents results on shifted terms, ask for the same months side by side. This process is not an audit, and it is not a daily habit. It is a single honest answer to the one-year mark. Past measurement protects the future. A project is a promise with a price.
Checking it once honestly is how you learn which promises to believe.